Large Bore Alloy 600
Structural Integrity and WSI are teaming up to share with you a recently completed project that involved the design, licensing, implementation and inspection of an industry-first; Optimized Weld Overlays (OWOLs) applied preemptively on four (4) reactor coolant pump discharge nozzle Alloy 600 welds.
You will learn:
- Summarize the technical basis of OWOL, including agreements reached with the NRC staff during the relief request review process.
- Present an overview of the site implementation project, including the tooling and team preparations and the welding experience.
- Provide details associated with the now finalized NRC's safety evaluation for MRP-169 for generic application of the OWOL concept.
- Discuss how leak-before-break requirements associated with weld overlay were fully addressed for this project.
Presented on: September 23, 2010
Instructors:
This e-mail address is being protected from spambots. You need JavaScript enabled to view it
from Structural Integrity and Jim Puzan from WSI